  Track Record 2008 - TNB – Nuni Substation Bangi (HYOSUNG CORPORATION)
Page 1 | 2 | 3 | 4 | 5 | 6 | 7
  
  
  
 
Details:-

Project Name
Cargo
Equiment Type
Client
Period
TNB – Nuni Substation Bangi
(HYOSUNG CORPORATION)

3 UNITS 240MVA TRANSFORMER

(Length 10.9m x Width 4.85m x Height 4.50m)

MULTI AXLE COMETTO TRAILER
(14 Axle Line x 2 File)
MISC
31 MARCH 2008


Description:-

·INLAND TRANSPORTATION OF 3 UNITS 240MVA TRANSFORMER @205MT
FROM SHIP NORTHPORT TO NUNI SUBSTATION BANGI, JACKING & SKIDDING ONTO FOUNDATION

 